For items exceeding $10,000 , contractors must typically obtain at least three quotes from Saudi manufacturers and provide a cost comparison to Aramco before finalizing a purchase.

A major pillar of Schedule G is the promotion of local industry within Saudi Arabia. The document enforces specific procurement guidelines : saudi aramco schedule g

Contractors are required to prioritize Saudi manufacturers, vendors, and carriers over international options. For items exceeding $10,000 , contractors must typically

Contractors must implement a Materials Management System to track receipt, usage, damage, and remaining stock. Contractors must implement a Materials Management System to

When Aramco provides materials, the contractor acts as a temporary custodian. Schedule G mandates strict accountability:

Materials provided by Aramco to the contractor at no cost, often for large-scale infrastructure like pipelines.

Monthly status reports are required, detailing physical locations (e.g., laydown yards or warehouses) and safety records for hazardous materials.